In partnership with the Government of Odisha, Tata Steel is committed to set up a 6 million tonne per annum integrated steel plant at Kalinganagar Industrial Complex at Duburi, in the Jajpur district. The Steel Works will be established in two modules of 3 million tonnes of steel each and when completed, will have a capacity of 6 million tonnes per annum.

Preliminary work on land acquisition, rehabilitation and resettlement is in full swing and the Company has sought grant for mining lease from the Odisha State Government. The order for equipment and services (as per MOU signed earlier) has been placed and several consignments have already arrived.

The total number of extended families to be rehabilitated in this area has been calculated at 1195. Special attention has been given to all the requirements of the families in rehabilitation colonies and resettlement camps that are fully equipped with all amenities. With Kalinganagar emerging as the steel hub of Odisha, Tata Steel will help boost the pace of industrialisation and socio-economic development, not only in the State but in the Country as well.
Kalinganagar – Project Highlights

  • MOU for the steel project was signed between the Government of Odisha and Tata Steel on November 17, 2004.  
  • As per the MoU, Odisha Government agreed to provide 3,471.808 acres of land, earlier acquired through the Industrial Development Corporation of Orissa.
  • MOU was also signed with the Nippon Steel Corporation on August 28, 2005 for offering technical assistance for the project.
  • When operational, the Kalinganagar Works is projected to generate revenues in the range of Rs 2,200 crores per annum and also provide direct and indirect employment to about 20,000 people.
  • As per the terms of the MoU, Government of Odisha would be allocating an iron ore mine to the Company on completion of 25% of the project work.
   

Details of the Plant Site

The proposed plant site happens to be a part of six revenue villages - Gobaraghati, Chandia, Gadapur, Nuagaon, Khurunti and Baragadia - of the Sukinda Tehesil in Jajpur District.

The specific details are given in the table below:

Sl. No Revenue Village Area (In Acres)
Private Land Government Land Total Land
1 Gobaraghati 731.600 61.940 793.540
2 Chandia 1083.810 263.345 1347.155
3 Nuagaon 90.70 15.82 106.52
4 Gadapur 388.49 135.749 524.239
5 Khurunti 128.006 0.540 128.546
6 Baragadia 236.78 123.63 360.41
  Total 2659.386 >601.024 3260.410